2022 Construction Projects

Updated 6/1/2022

 

Updated 6/13/2022

 CSAH 3 (105th Ave NE) from Gilman to Morrison County

  • Culvert replacement, bituminous reclamation & new bituminous surface.
  • Culverts are replaced and the first lift of pavement placed. Pavement anticipated to be complete on 6/15 with gravel shouldering and striping remaining.

 CSAH 5 (115th St NE) from CR 62 in Gilman to Mille Lacs County

  • Underseal and Bituminous Overlay.
  • Paving is finished with gravel shouldering and striping remaining.

CSAH 22 (165th St NE) from CSAH 14 to CSAH 7

  • 1st lift of pavement placed.
  • Top lift of pavement planned for later in the week of June 13th.

 CR 70 (125th Ave NE) from CSAH 14 to CSAH 7

  • Bituminous reclamation and new bituminous surface.
  • 1st lift of pavement has been placed with the top lift of pavement planned for later in the week of June 13th.

CSAH 12 (Pine Rd NE) from MN TH 25 to CSAH 3

  • Bituminous overlay planned for end of June or early July.

 CR 50 (30th St NE) at Existing Bridge L0030

  • Road/Bridge is open and project complete.

 CR 51 (55th St NE) at Existing Bridge L0032 (Approx. 0.4 miles east of TH 25)

  • Bridge replacement planned for late July or Early August 2022. Road will be closed at the Bridge.

 CR 67 (155th Ave NE) at Existing Bridge 05519 (Approx. 0.2 miles north of TH 23)

  • Bridge replacement planned for late July 2022 or early August 2022. Road will be closed at the Bridge. 

 CR 80 (35th Ave NE) at Existing Bridge L5806

  • Road/Bridge is open and project complete.